Project brief

Ancora Foundations was appointed to deliver a comprehensive piling package for the redevelopment of St Mildred's Church in Lee, South East London, providing both foundation support for a new church and community hall together with a contiguous piled retaining wall for a new basement. The project comprised approximately 61 No. 300mm diameter bearing piles together with a 300mm diameter contiguous piled retaining wall, delivering a complete foundation and basement support solution.

category
location

Lee, London SE12

Piling Solution

Combined SFA & CFA Bored Piles

Bearing Piles

300mm contiguous piled wall @ 500mm centres

Ground Conditions

Made Ground, Head Deposits & London Clay

Groundwater

Approx. 1.4–1.6m below ground level

Application

Church redevelopment, community hall & basement

Two Men Working in a Factory
Factory Interior

Scope of Works

  • Installation of 61 No. 300mm diameter bearing piles.

  • Construction of a 300mm diameter contiguous piled retaining wall at 500mm centres.

  • Combination of Sectional Flight Auger (SFA) piling and Continuous Flight Auger (CFA) piling techniques.
  • Installation of reinforced concrete pile cages.

  • Basement support and earth retention solution.

Engineering Challenges

Restricted working space within a live church environment, construction adjacent to
existing buildings, formation of a new basement, variable Made Ground over Head Deposits
and London Clay, and shallow groundwater required a carefully planned piling
methodology and construction sequence.